No. Only subcontractors, sub-subcontractors and suppliers who do not have a direct contract with the project owner are required to send a Pre-lien Notice Letter (for each month that is unpaid) before filing a mechanic’s lien affidavit with the county.
Related questions and answers
We do not recommend filing a copy of your invoices in the Property Records with your Lien Affidavit. However you must retain copies of them as you may require them in the future.
The deadline to file a mechanic's lien depends on a contractor's role and the type of project. For Commercial Projects (Private), the following charts specify the required documents and the last date to submit them. We have separated the charts by type of contractor. It is essential to know that the last day to file or submit a lien document is always the 15th day of every month.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED BEFORE DECEMBER 31ST, 2021
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL BE THE EARLIEST BUSINESS DAY.
FOR CLAIMS RESULTING FROM A CONTRACT SIGNED AFTER JANUARY 1ST, 2022
IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.
Original (General) Contractor - Constitutional - Mechanic’s Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of: a) Written Termination b) Abandonment of Project c) Settlement or: d) Completion of the Contract | Commercial Projects (Private) 🔗 | ||
Pre-lien Notice to Property Owner is Not Required |
File the Lien Affidavit On or Before: | ||
January | None | May 15th | |
February | None | June 15th | |
March | None | July 15th | |
April | None | August 15th | |
May | None | September 15th | |
June | None | October 15th | |
July | None | November 15th | |
August | None | December 15th | |
September | None | January 15th | |
October | None | February 15th | |
November | None | March 15th | |
December | None | April 15th |
Subcontractor (1st Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
Sub-subcontractor (2nd Tier) Lien Requirements | |||
---|---|---|---|
Chart of Filing Deadlines | |||
Month of Activity | Commercial Projects (Private) 🔗 | ||
Send Invoice by: | Send Pre-lien Notice to Property Owner and Original Contractor by: |
File the lien by the following date OR within 30 days after the overall project is complete**. | |
January | March 15th | April 15th | May 15th |
February | April 15th | May 15th | June 15th |
March | May 15th | June 15th | July 15th |
April | June 15th | July 15th | August 15th |
May | July 15th | August 15th | September 15th |
June | August 15th | September 15th | October 15th |
July | September 15th | October 15th | November 15th |
August | October 15th | November 15th | December 15th |
September | November 15th | December 15th | January 15th |
October | December 15th | January 15th | February 15th |
November | January 15th | February 15th | March 15th |
December | February 15th | March 15th | April 15th |
IMPORTANT:
**You can file a lien affidavit 30 days after completing the overall project only if you sent the pre-lien notice for that specific month on time.
|
In the mechanics lien process, a lien release is a document filed with the Property Records Office which requests to remove a lien previously filed in a property. The lien release states the claim filed has been paid and releases any rights to file a new lien for the amount paid.
No. The Texas constitution only allows a general contractor and those who have a direct contract with the owner to assert a constitutional lien (this lien does not require sending written prelien notices). Subcontractors do not have a direct contract with the owner, therefore those construction liens are called Mechanic’s Lien Affidavit. Exception: If a subcontractor has a direct contract with the project owner, then it might be able to assert a constitutional lien against the project.
Yes, you do not have to leave your office to file your liens anymore. Texas Easy Lien now has the capability of notarizing and filing your documents online.