Bond Claim

What are the deadlines to file a construction bond claim?

Deadlines for bond claims are much like those for liens. Subcontractors, sub-subcontractors, and suppliers must send a notice of bond claim with a sworn account statement by the 15th day of the third month after the work or material delivery month. These documents should be sent to both the Surety Company and the General Contractor. The charts below categorize contractors and outline necessary documents and submission deadlines.

NOTE: IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.

Subcontractors and Suppliers (Contractor w/ Original Contractor)
Month when labor or materials were delivered: PUBLIC PROJECT (not federal)
Mail Bond Claim and Sworn Statement of Account to Surety and Original Contractor on or before:
January April 15th
February May 15th
March June 15th
April July 15th
May August 15th
June September 15th
July Ocitober 15th
August November 15th
September December 15th
October January 15th
November February 15th
December March 15th

Sub-subcontractors and suppliers without a direct contract with the prime contractor (those on the second tier and below) must first send a notice only to the general (prime) contractor by the 15th day of the second month after the work was done. This notice can be copies of your unpaid invoices along with a signed cover letter indicating the outstanding amounts. You don’t need to provide a sworn statement of account with this notice.

Sub-Subcontractor and Suppliers (Contact w/ Subcontractor)
Month when labor or materials were delivered: PUBLIC PROJECTS (not federl)
Mail Early Notice to Original Contractor on or before: Mail Bond Claim Notice and Sworn Statement of Account to Surety and Original Contactor on or before:
January March 15th April 15th
February April 15th May 15th
March May 15th June 15th
April June 15th July 15th
May July 15th August 15th
June August 15th September 15th
July September 15th October 15th
August October 15th November 15th
September November 15th December 15th
October December 15th January 15th
November January 15th February 15th
December February 15th March 15th