What is the deadline to file a mechanic’s lien?

The deadline to file a mechanic’s lien depends on a contractor’s role and the type of project.
For Commercial Projects (Private), the following charts specify the required documents and the last date to submit them.
We have separated the charts by type of contractor. It is essential to know that the last day to file or submit a lien document is always the 15th day of every month.

IF THE 15th OF THE MONTH FALLS ON A WEEKEND OR A HOLIDAY, THE LAST DAY TO FILE A VALID LIEN WILL EXTEND TO THE NEXT BUSINESS DAY AFTER THAT WEEKEND OR HOLIDAY.

Original (General) Contractor – Constitutional – Mechanic’s Lien Requirements
Chart of Filing Deadlines
Month of:
a) Written Termination
b) Abandonment of Project
c) Settlement or:
d) Completion of the Contract
Commercial Projects (Private) 🔗
Pre-lien Notice to Property Owner is
Not Required
File the Lien Affidavit On or Before:
January None May 15th
February None June 15th
March None July 15th
April None August 15th
May None September 15th
June None October 15th
July None November 15th
August None December 15th
September None January 15th
October None February 15th
November None March 15th
December None April 15th
Subcontractor (1st Tier) Lien Requirements
Chart of Filing Deadlines
Month of Activity Commercial Projects (Private) 🔗
Send Invoice by: Send Pre-lien Notice
to Property Owner and Original Contractor by:
File the lien by the following date OR within 30 days after the overall project is complete**.
January March 15th April 15th May 15th
February April 15th May 15th June 15th
March May 15th June 15th July 15th
April June 15th July 15th August 15th
May July 15th August 15th September 15th
June August 15th September 15th October 15th
July September 15th October 15th November 15th
August October 15th November 15th December 15th
September November 15th December 15th January 15th
October December 15th January 15th February 15th
November January 15th February 15th March 15th
December February 15th March 15th April 15th
IMPORTANT:

​* * You can file a lien affidavit 30 days after completing the overall project, but only if you sent the pre-lien notice for that specific month on time.

Sub-subcontractor (2nd Tier) Lien Requirements
Chart of Filing Deadlines
Month of Activity Commercial Projects (Private) 🔗
Send Invoice by: Send Pre-lien Notice
to Property Owner and Original Contractor by:
File the lien by the following date OR within 30 days after the overall project is complete**.
January March 15th April 15th May 15th
February April 15th May 15th June 15th
March May 15th June 15th July 15th
April June 15th July 15th August 15th
May July 15th August 15th September 15th
June August 15th September 15th October 15th
July September 15th October 15th November 15th
August October 15th November 15th December 15th
September November 15th December 15th January 15th
October December 15th January 15th February 15th
November January 15th February 15th March 15th
December February 15th March 15th April 15th
IMPORTANT:

** You can file a lien affidavit 30 days after completing the overall project, but only if you sent the pre-lien notice for that specific month on time.

Residential Projects
Month of Activity Subcontractor - deadlines
Pre-lien Notice to Owner and Original Contractor Last Day to File the Lien Affidavit
January March 15th April 15th
February April 15th May 15th
March May 15th June 15th
April June 15th July 15th
May July 15th August 15th
June August 15th September 15th
July September 15th October 15th
August October 15th November 15th
September November 15th December 15th
October December 15th January 15th
November January 15th February 15th
December February 15th March 15th
Residential Projects
Month of:
a) Written Termination
b) Completion
c) Abandonment
Original contractor - deadlines
Pre-lien Notice to Owner Last Day to File the Lien Affidavit
January None April 15th
February None May 15th
March None June 15th
April None July 15th
May None August 15th
June None September 15th
July None October 15th
August None November 15th
September None December 15th
October None January 15th
November None February 15th
December None March 15th

Get your mechanic’s lien documents in just 15 minutes

Holiday Closure Announcement

We wish you a joyful holiday season! Please note that all counties will be closed during the holidays. Any documents submitted during their closure will be recorded when they reopen.

 

Additionally, our office and support agents will also be unavailable on the following dates:
  • December 24th and 25th (Christmas)
  • December 31st and January 1st (New Year’s)
 
Thank you for your understanding, and we look forward to assisting you when we return! Happy Holidays!